Interconnection works Loma Blanca are progressing

We continue developing in a continuous manner the INTERCONNECTION WORKS WITH 132 kV HIGH VOLTAGE POWER LINES of Eolic Parks Loma Blanca I&III and VI located between the cities of Trelew and Puerto Madryn, Chubut, for POWER CHINA L.T.D.. The detail engineering is making great progress, as well as the arrival of equipment and materials to the site. Approximately 90% of the purchase orders for the main equipment have been completed, and progress is made in rehearsals of their reception.

The civil works of high voltage power lines have been started and the laying of a very complex 2 km stretch was completed in record time (less than 60 days). The works included crossing below three 330 and 500kV lines with many special structures. Besides, the electromechanical assembly of the stations was started.

Construction of the PYLBO Line advanced as well, with over 50 foundations made and the assembly of 46 structures, with the latter’s dressing already started and the laying of conductors to begin soon.